Nepal plans to import 1,154 MW of electricity from India this winter

Nepal is preparing to import up to 1,154 megawatts of electricity from India during the coming dry season as the country faces a significant gap between domestic generation and winter demand. The Nepal Electricity Authority (NEA) says the plan is necessary after floods and landslides damaged hydropower plants and transmission infrastructure across the country.

The NEA estimates that only around 1,218 MW of electricity will be available from domestic generation during the dry months, when water levels in rivers decline and hydropower production falls. At the same time, national peak demand is projected at around 2,292 MW, leaving a substantial supply gap that will need to be covered through imports and other measures.

Under the proposed plan, around 600.8 MW would be imported through the Dhalkebar-Muzaffarpur transmission line, while another 54 MW would come through the Tanakpur-Mahendranagar connection. The authority also plans to import around 350 MW through transmission links with Bihar and Uttar Pradesh, along with another 150 MW through the real-time or bilateral mechanism.

The planned imports are particularly important because recent disasters have caused major damage to Nepal’s electricity infrastructure. The August 26 Bhotekoshi flood damaged hydropower projects and transmission facilities in Rasuwa and Nuwakot, affecting electricity generation and the ability to evacuate power into the national grid.

The NEA is also working to strengthen electricity distribution inside the Kathmandu Valley, where winter demand is expected to rise. Last winter, peak demand in the Valley reached around 700 MW, and officials estimate demand could increase by about 10 percent this year. The authority plans to shift loads between substations and make greater use of newly developed transmission and underground cable infrastructure.

At the same time, the NEA is working to repair flood-damaged transmission infrastructure. The 220 kV Trishuli-Chilime system suffered significant damage, including the destruction of the Trishuli 3B Hub substation. The authority is studying options for rebuilding the substation at a safer location and restoring affected power links.

The Kulekhani reservoir is also expected to play an important role in meeting winter demand. However, the authority has already been using Kulekhani more heavily than usual to compensate for electricity lost after the floods, putting greater importance on careful management of available water resources for the dry months.

India has already approved additional electricity exports to Nepal, although arrangements for the full winter requirement will depend on further approvals and agreements. The NEA is therefore combining domestic generation, electricity imports, reservoir management and transmission improvements to maintain a reliable supply during the coming winter.

The plan highlights the continuing impact of this year’s natural disasters on Nepal’s energy sector. With several hydropower facilities still affected, securing enough electricity for households, businesses and industries will remain a major priority as winter demand begins to rise.